What happens if a land-disturbing activity has not begun within 180 days after plan approval?

The plan is automatically approved

The approved erosion and sediment control plan may be reevaluated

When a land-disturbing activity has not commenced within 180 days following the approval of an erosion and sediment control plan, the approved plan may be reevaluated. This aspect of the regulation acknowledges that conditions on the site or surrounding environment may have changed since the plan was originally approved. Factors such as new regulations, environmental considerations, or site-specific changes could affect the suitability or effectiveness of the original plan.

The requirement for reevaluation ensures that the plan still meets current standards and best practices for erosion and sediment control, ultimately serving to protect the environment and local water quality. By being subject to reevaluation, the plan can be updated to reflect any modifications needed due to changing conditions. This provision emphasizes the importance of proactive management in land-disturbing activities rather than allowing outdated plans to remain in use without scrutiny.

Get further explanation with Examzify DeepDiveBeta

The activity is exempt from compliance

Nothing happens; the plan remains valid